I suspect with the amount of time Joe's people are putting into this, they're not going to be making the amount of money they expected. But hopefully it'll work out well.
cleaned costs good material pay railroad rid site sites storage three tourist worn
We're getting rid of all the material we can't use. It's worn out or no good for the tourist railroad and we're also getting our three storage sites cleaned up. One storage site costs us $300 a month, so we won't have to pay that anymore.
design designed late miles months nine october railroad running trains
The railroad was designed in late 1868 and running trains in October of 1869, nine months after its design. We have been working for 14 years and have 1.4 miles built.