known slope
This was in a slope we've known to be a problem.
failures history
We hadn't had a history of significant failures in this area.
activity based built deferred design list programmed ready took
We had some activity in March, and based on that we took it off the deferred list and were working on getting it programmed for repair. We were getting ready to do some remedial design work, and it was scheduled to be built in the spring.